dc.identifier.citationArellano, M. J. (2022). Implementación de la metodología Lean Construction en el proyecto construcción de Compañía de Bomberos Nº 47 para optimizar los costos y plazos, en el distrito de Oxapampa, año 2022 [Tesis de licenciatura, Universidad Privada del Norte]. Repositorio de la Universidad Privada del Norte. https://hdl.handle.net/11537/33254es_PE
dc.identifier.other690.068 AREL/I 2022es_PE
dc.identifier.urihttps://hdl.handle.net/11537/33254
dc.description.abstractEste presente trabajo investigativo tiene como propósito, utilizar la metodología Lean Construction (LC) para evaluar el plazo y costo en el proyecto de Construcción de Compañía de Bomberos Nº 47 en el distrito de Oxapampa. La investigación es de orientación aplicada, enfoque cuantitativo y diseño no experimental – correlacional. La población quedó conformada por todas las obras públicas del distrito de Oxapampa que puedan ser ejecutadas aplicando la metodología Lean Construction, tomando como muestra la Construcción de la Compañía de Bomberos Nº 47 del distrito de Oxapampa, de dicho presupuesto se seleccionaron las partidas correspondientes al título Estructuras Metálicas. La técnica manejada para recoger los datos es la observación y el análisis documental, con su instrumento la ficha de registro de datos. Se concluye que al implementar la metodología LC para evaluar el plazo en la construcción de la Compañía de Bomberos Nº 47 del distrito de Oxapampa, 2022; se obtuvo que la metodología Lean Construction mejora significativamente el plazo para la construcción de la Compañía de Bomberos Nº 47 del distrito de Oxapampa, 2022, puesto que se logra una reducción del plazo de ejecución de las partidas analizadas en un 7.69%. Al implementar la metodología LC para evaluar el costo en la construcción de la Compañía de Bomberos Nº 47 del distrito de Oxapampa, 2022, se determinó que mejora significativamente el costo ya que se logra optimizar el presupuesto general en un 13.00%.es_PE
dc.description.abstractThe purpose of this present investigative work is to use the Lean Construction (LC) methodology to evaluate the term and cost in the Construction project of Fire Company No. 47 in the district of Oxapampa. The research is applied orientation, quantitative approach and non-experimental design - correlational. The population was made up of all the public works of the Oxapampa district that can be executed applying the Lean Construction methodology, taking as a sample the Construction of the Fire Company No. 47 of the Oxapampa district, from said budget the items corresponding to the title were selected. Metallic structures. The technique used to collect the data is observation and documentary analysis, with its instrument the data record sheet. It is concluded that by implementing the LC methodology to evaluate the term in the construction of the Fire Company No. 47 of the Oxapampa district, 2022; It was obtained that the Lean Construction methodology significantly improves the term for the construction of the Fire Company No. 47 of the Oxapampa district, 2022, since a reduction of the execution term of the analyzed items is achieved by 7.69%. By implementing the LC methodology to evaluate the cost in the construction of the Fire Company No. 47 of the Oxapampa district, 2022, it was determined that it significantly improves the cost since it is possible to optimize the general budget by 13.00%.es_PE
dc.description.uriTesises_PE
dc.formatapplication/pdfes_PE
dc.formatapplication/msword
dc.language.isospaes_PE
dc.publisherUniversidad Privada del Nortees_PE
dc.rightsinfo:eu-repo/semantics/openAccesses_PE
dc.rightsAtribución-NoComercial-CompartirIgual 3.0 Estados Unidos de América*
dc.rights.urihttps://creativecommons.org/licenses/by-nc-sa/3.0/us/*
dc.sourceUniversidad Privada del Nortees_PE
dc.sourceRepositorio Institucional - UPNes_PE
dc.subjectConstrucciónes_PE
dc.subjectCostos de construcciónes_PE
dc.subjectAlbañileríaes_PE
dc.subjectMetodología Lean Constructiones_PE
dc.subjectPlazos para la construcciónes_PE
dc.subjectEdificacioneses_PE
dc.titleImplementación de la metodología Lean Construction en el proyecto construcción de Compañía de Bomberos Nº 47 para optimizar los costos y plazos, en el distrito de Oxapampa, año 2022es_PE
dc.typeinfo:eu-repo/semantics/bachelorThesises_PE
thesis.degree.grantorUniversidad Privada del Norte. Facultad de Ingenieríaes_PE
thesis.degree.levelTítulo Profesionales_PE
thesis.degree.disciplineIngeniería Civiles_PE
thesis.degree.nameIngeniero Civiles_PE
dc.publisher.countryPEes_PE
dc.subject.ocdehttps://purl.org/pe-repo/ocde/ford#2.01.01es_PE
thesis.degree.programPregradoes_PE
dc.description.sedeBreñaes_PE
renati.advisor.dni45417237
renati.advisor.orcidhttps://orcid.org/0000-0003-1609-1704es_PE
renati.author.dni70506394
renati.discipline732016es_PE
renati.jurorVereau Miranda, Edmundo
renati.jurorRabanal chavez, Erick Humberto
renati.jurorCampos Vasquez, Neicer
renati.levelhttp://purl.org/pe-repo/renati/level#tituloProfesionales_PE
renati.typehttp://purl.org/pe-repo/renati/type#tesises_PE
dc.relation.conformsto13%es_PE


Ficheros en el ítem

Thumbnail
Thumbnail
Thumbnail
Thumbnail
Thumbnail

Este ítem aparece en la(s) siguiente(s) colección(ones)

Mostrar el registro sencillo del ítem

info:eu-repo/semantics/openAccess
Excepto si se señala otra cosa, la licencia del ítem se describe como info:eu-repo/semantics/openAccess