dc.identifier.citationDíaz, A. L. (2015). Optimización de la gestión y dirección de la construcción del tramo III del acceso principal al proyecto Conga aplicando metodología de los estándares del PMBOK y Last Planner System, 2014 (Tesis de licenciatura). Repositorio de la Universidad Privada del Norte. Recuperado de https://hdl.handle.net/11537/6902es_PE
dc.identifier.other625.7 DIAZ 2015es_PE
dc.identifier.urihttps://hdl.handle.net/11537/6902
dc.description.abstractRESUMEN El presente trabajo de investigación se llevó a cabo en el proyecto: “Construcción del Tramo III del Acceso Principal al Proyecto Conga”, ubicado entre los distritos de Huasmín y Sorochuco, Provincia de Celendín y La Encañada, Provincia de Cajamarca, Departamento de Cajamarca – Perú, realizada en el año 2014, donde se aplicó metodología de los estándares del PMBOK y Last Planner System, reconocidos a nivel mundial. Este estudio corresponde a una investigación No Experimental Transeccional Descriptiva y la recolección de datos tuvo dos escenarios, no en gabinete y otro en obra mediante Fuentes Primarias. Para la implementación de la metodología, la supervisión del Área de Construcción del Proyecto Conga ha aplicado los estándares del PMBOK y Last Planner System en el inicio, planificación, ejecución, seguimiento y control y cierre del proyecto. En la etapa de Inicio del Proyecto se realizó el alcance del proyecto y se definieron los interesados. En la etapa de Planificación se elaboraron diferentes planes de Dirección para el desarrollo del proyecto, se definió el Cronograma y el Presupuesto. Durante la Etapa de Ejecución y Seguimiento y Control se empleó la herramienta de Gestión del Valor Ganado y se insertó Last Planner System para la programación de trabajos semana a semana. Concluyendo que la aplicación los estándares del PMBOK y Last Planner System optimizan la gestión y dirección de proyectos y se asegura el cumplimiento del Presupuesto aprobado y del Cronograma planificado teniendo como Indicadores de Estado del proyecto: CPI y SPI.es_PE
dc.description.abstractABSTRACT This research was conducted in the project: "Construction of Section III of the Main Access to Conga’s Project," located between the districts of Huasmín and Sorochuco, Province Celendín and Encañada, Province of Cajamarca, Department of Cajamarca - Peru, held in 2014, where methodology and standards PMBOK Last Planner System, recognized globally applied. This study is a no experimental research transectional Descriptive and data collection had two scenarios, one in cabinet and another on site with Primary Sources. For the implementation of the methodology, supervision of the construction area of Conga’s Project has applied standards PMBOK and Last Planner System in initiating, planning, executing, monitoring and control and project closure. In the Project Initiation stage the scope of the project was conducted and stakeholders were defined. In the planning stage direction different plans for the project were developed, it defined the schedule and budget. During the implementation phase, monitoring and control tool Earned Value Management is used and inserted Last Planner System for scheduling jobs every week. Concluding that the application standards PMBOK Last Planner System and optimize the management and direction of projects and compliance with the approved budget and schedule as planned taking Status Indicators project ensures: CPI and SPI.es_PE
dc.description.uriTesises_PE
dc.formatapplication/pdfes_PE
dc.formatapplication/mswordes_PE
dc.language.isospaes_PE
dc.publisherUniversidad Privada del Nortees_PE
dc.rightsinfo:eu-repo/semantics/closedAccesses_PE
dc.sourceUniversidad Privada del Nortees_PE
dc.sourceRepositorio Institucional - UPNes_PE
dc.subjectPavimentoses_PE
dc.subjectConstrucción de carreterases_PE
dc.subjectMineríaes_PE
dc.titleOptimización de la gestión y dirección de la construcción del tramo III del acceso principal al proyecto Conga aplicando metodología de los estándares del PMBOK y Last Planner System, 2014es_PE
dc.typeinfo:eu-repo/semantics/bachelorThesises_PE
thesis.degree.grantorUniversidad Privada del Norte. Facultad de Ingenieríaes_PE
thesis.degree.levelTítulo Profesionales_PE
thesis.degree.disciplineIngeniería Civiles_PE
thesis.degree.nameIngeniero Civiles_PE
dc.publisher.countryPEes_PE
dc.subject.ocdehttps://purl.org/pe-repo/ocde/ford#2.01.01es_PE
thesis.degree.programPregradoes_PE
dc.description.sedeCajamarcaes_PE
renati.advisor.dni26617213
renati.author.dni47116711
renati.discipline732016es_PE
renati.levelhttps://purl.org/pe-repo/renati/level#tituloProfesionales_PE
renati.typehttps://purl.org/pe-repo/renati/type#tesises_PE


Ficheros en el ítem

Thumbnail
Thumbnail
Thumbnail
Thumbnail

Este ítem aparece en la(s) siguiente(s) colección(ones)

Mostrar el registro sencillo del ítem