dc.contributor.advisorColonio García, Luis
dc.contributor.authorGonzales Ventura, Carlos Alfredo
dc.date.accessioned2018-12-10T15:43:45Z
dc.date.available2018-12-10T15:43:45Z
dc.date.issued2018
dc.identifier.citationGonzales, C. A. (2018). Aplicación de la metodología Last Planner en el planeamiento, programación y control en la construcción de obras públicas de riego (Trabajo de suficiencia profesional). Repositorio de la Universidad Privada del Norte. Recuperado de http://hdl.handle.net/11537/14335es_PE
dc.identifier.other624 GONZ 2018es_PE
dc.identifier.urihttps://hdl.handle.net/11537/14335
dc.description.abstractRESUMEN Actualmente el Last Planner System se ha implementado en diversas empresas alrededor del mundo debido a su alto impacto en los resultados. Las empresas constructoras trabajan en un sector donde tienen como principal característica la enorme variabilidad de sus parámetros, el Last Planner System tiene como objetivo principal gestionar la reducción de esta variabilidad. En los últimos años en el Perú, ya hay empresas como Edifica, VyV Bravo que han logrado implementar con éxito el Last Planner System, básicamente en obras en edificaciones. En el mercado peruano hay una gran brecha en infraestructura en todo tipo de proyectos (según plan nacional de infraestructura 2016 - 2025), lo que nos indica que el sector construcción se debe convertir en uno de los principales motores de la economía peruana. Muchas de las empresas que participan en los proyectos de infraestructura especialmente con el estado no logran ejecutar y cumplir con las fechas acordadas con las entidades, de acuerdo a los contratos esto produce diversas, resultando en un enorme perjuicio económico en sus ingresos, lo que perjudica su liquidez y su utilidad. La presente Tesis aplica el Last Planner System en obras de riego con el estado donde la empresa ejecutora tiene como principal problema la entrega a tiempo de sus obras por lo que definimos que al aplicar el sistema de gestión Last Planner System en la programación, control en obras públicas de riego se consigue disminuir los plazos de ejecución. Con los resultados obtenidos en la evaluación de la aplicación nos damos cuenta que la Tesis consigue validar el problema principal de conseguir mejorar estos plazos, durante la ejecución de la obra.es_PE
dc.description.abstractABSTRACT Currently the Last Planner System has been implemented in several companies around the world due to its high impact on results. The construction companies’ work in a sector where the main feature is the enormous variability of its parameters, the Last Planner System has as main objective to manage the reduction of this variability. In recent years in Peru, there are companies such as Edifica, VyV Bravo that have managed to successfully implement the Last Planner System, basically in building works. In the Peruvian market there is a large infrastructure gap in all types of projects (according to national infrastructure plan 2016 - 2025), which indicates that the construction sector must become one of the main engines of the Peruvian economy. Many of the companies that participate in the infrastructure projects, especially with the state, fail to execute and comply with the dates agreed with the entities. According to the contracts, this produces diverse results, resulting in a huge economic loss in their income, which hurts its liquidity and its usefulness. This Thesis applies the Last Planner System in irrigation works with the state where the executing company has as main problem the timely delivery of their works so we define that when applying the Last Planner System management system in the programming, control in public works of irrigation is achieved to reduce the execution deadlines. With the results obtained in the evaluation of the application we realize that the Thesis manages to validate the main problem of getting to improve these deadlines, during the execution of the work.es_PE
dc.description.uriTrabajo de suficiencia profesionales_PE
dc.formatapplication/pdfes_PE
dc.language.isospaes_PE
dc.publisherUniversidad Privada del Nortees_PE
dc.rightsinfo:eu-repo/semantics/openAccesses_PE
dc.rightsAtribución-NoComercial-CompartirIgual 2.5 Perúes_PE
dc.rights.urihttps://creativecommons.org/licenses/by-nc-sa/2.5/pe/*
dc.sourceUniversidad Privada del Nortees_PE
dc.sourceRepositorio Institucional - UPNes_PE
dc.subjectIngeniería Civiles_PE
dc.subjectConstrucciónes_PE
dc.subjectInversiones públicases_PE
dc.subjectGestión de la construcciónes_PE
dc.titleAplicación de la metodología Last Planner en el planeamiento, programación y control en la construcción de obras públicas de riegoes_PE
dc.typeinfo:eu-repo/semantics/bachelorThesises_PE
thesis.degree.grantorUniversidad Privada del Norte. Facultad de Ingenieríaes_PE
thesis.degree.levelTítulo Profesionales_PE
thesis.degree.disciplineIngeniería Civiles_PE
thesis.degree.nameIngeniero Civiles_PE
dc.publisher.countryPEes_PE
dc.subject.ocdehttps://purl.org/pe-repo/ocde/ford#2.01.01es_PE
thesis.degree.programPregradoes_PE
dc.description.sedeLos Olivoses_PE
renati.discipline732016es_PE
renati.levelhttps://purl.org/pe-repo/renati/level#tituloProfesionales_PE
renati.typehttps://purl.org/pe-repo/renati/type#trabajoDeSuficienciaProfesionales_PE


Ficheros en el ítem

Thumbnail

Este ítem aparece en la(s) siguiente(s) colección(ones)

Mostrar el registro sencillo del ítem

info:eu-repo/semantics/openAccess
Excepto si se señala otra cosa, la licencia del ítem se describe como info:eu-repo/semantics/openAccess