dc.contributor.advisorBueno Ponce, Carlos Alberto
dc.contributor.authorAnchayhua Chate, Zenaida
dc.date.accessioned2019-03-27T23:34:40Z
dc.date.available2019-03-27T23:34:40Z
dc.date.issued2018-07-02
dc.identifier.citationAnchayhua, Z. (2018). Plan de mejora para incrementar la productividad del proceso de instalación de postes de suministros eléctricos en la empresa Prodiel Perú S. A. C. en el año 2017 [Trabajo de suficiencia profesional, Universidad Privada del Norte]. Repositorio de la Universidad Privada del Norte. https://hdl.handle.net/11537/15221es_PE
dc.identifier.other658.3124 ANCH 2018es_PE
dc.identifier.urihttps://hdl.handle.net/11537/15221
dc.description.abstractLa presente investigación tuvo como objetivo principal incrementar la productividad del proceso de instalación de postes de suministro eléctrico en la empresa Prodiel Perú S.A.C. en el año 2017, para lograr ello en primer lugar se analizó la situación inicial del proceso de instalación de postes mediante el uso de diagrama de Ishikawa y diagrama de Pareto, carta balance para medir el tiempo productivo, contributivo, no contributivo, se utilizaron diagramas de operaciones y actividades del proceso, asimismo se determinaron indicadores de gestión para el análisis y diagnóstico de las actividades que evidencian la realidad problemática dada por la baja productividad en el proceso materia de estudio. Posteriormente, se desarrolló el diseño del plan de mejora basado en el ciclo de Deming, el cual consta de etapas tales como planear, hacer, verificar, actuar con ello se buscó que el plan de mejora compuesto de acciones específicas logre incrementar la productividad, dichas acciones fueron: la adquisición de nuevas herramientas para ejecución del trabajo, el programa de capacitación al personal operativo y alquiler de equipos en obra, esto permitió reducir el tiempo del proceso de instalación de 335 minutos a 170 minutos, asimismo incrementar la cantidad de postes instalados promedio mensual de 88 postes a 139 postes, lograr el aumento del indicador de productividad promedio mensual en el año 2016 de 7,86 pp/hh a una productividad promedio mensual en el año 2017 de 12,44 pp/hh, esto evidenció un incremento porcentual de 58%, lo que confirma el beneficio operacional del plan de mejora, asimismo se incrementaron la tasa de capacitación de 0% a 100% en beneficio de los trabajadores del área analizada. Finalmente, se determinó que el impacto económico del plan de mejora pudo generar un beneficio económico de S/. 38 145,18 soles, considerando un costo de implementación de S/. 33 907,60 soles, asimismo se determinó un ratio costo-beneficio de 1,12, lo cual señala que el plan de mejora fue viable económicamente para el área de obras y para la empresa PRODIEL PERÚ S.A.C. en el año 2017.es_PE
dc.description.abstractThe main objective of this research was to increase the productivity of the installation process of power supply poles in the Prodiel Perú S.A.C. company in the year 2017. To achieve this, the initial situation of the pole installation process was first analyzed using the Ishikawa diagram and Pareto Diagrams, balances were used to measure the productive, contributory, non-contributory time, operation diagrams and process activities, as well as management indicators for the analysis and diagnosis of the activities that show the problematic reality given for the low productivity in the process object of study. Subsequently, the design of the improvement plan was developed based on the Deming cycle, which consists of stages such as planning, doing, verifying and acting with it. It was sought that the improvement plan composed of specific actions would increase productivity, these actions were: the acquisition of new tools for the execution of the work, the training program for the operative personnel and the equipment rental in the site, this allowed to reduce the time of the installation process from 335 minutes to 170 minutes, and also increase the monthly average of installed poles. 88 posts to 139 posts, achieve the increase of the average monthly productivity indicator in 2016 from 7,86 pp / hh to an average monthly productivity of 12,44 pp / hh in 2017, which shows a percentage increase of 58%, confirming the benefit The improvement plan also increased the training rate from 0% to 100% for the benefit of the work in the analyzed area. Finally, it was determined that the economic impact of the improvement plan could generate an economic benefit of S /. 38 145,18 soles, considering an implementation cost of S /. 33 907,60 soles, a cost-benefit ratio of 1,12 was also determined, which indicates that the improvement plan was economically viable for the works area and for the PRODIEL PERÚ S.A.C. company in 2017.
dc.description.uriTrabajo de suficiencia profesionales_PE
dc.formatapplication/pdfes_PE
dc.formatapplication/mswordes_PE
dc.language.isospaes_PE
dc.publisherUniversidad Privada del Nortees_PE
dc.rightsinfo:eu-repo/semantics/openAccesses_PE
dc.rightsAtribución-NoComercial-CompartirIgual 3.0 Estados Unidos de América
dc.rights.urihttps://creativecommons.org/licenses/by-nc-sa/3.0/us/*
dc.sourceUniversidad Privada del Nortees_PE
dc.sourceRepositorio Institucional - UPNes_PE
dc.subjectProductividades_PE
dc.subjectInstalaciones eléctricases_PE
dc.subjectElectricidades_PE
dc.subjectEquipos electrónicoses_PE
dc.subjectProductivity
dc.subjectLight posts
dc.titlePlan de mejora para incrementar la productividad del proceso de instalación de postes de suministros eléctricos en la empresa Prodiel Perú S. A. C. en el año 2017es_PE
dc.typeinfo:eu-repo/semantics/bachelorThesises_PE
thesis.degree.grantorUniversidad Privada del Norte. Facultad de Ingenieríaes_PE
thesis.degree.levelTítulo Profesionales_PE
thesis.degree.disciplineIngeniería Industriales_PE
thesis.degree.nameIngeniero Industriales_PE
dc.publisher.countryPEes_PE
dc.subject.ocdehttps://purl.org/pe-repo/ocde/ford#2.11.04es_PE
thesis.degree.programPregradoes_PE
dc.description.sedeLos Olivoses_PE
renati.advisor.dni40747598
renati.advisor.orcidhttps://orcid.org/0000-0002-5473-6668
renati.author.dni40881684
renati.discipline722026es_PE
renati.levelhttps://purl.org/pe-repo/renati/level#tituloProfesionales_PE
renati.typehttps://purl.org/pe-repo/renati/type#trabajoDeSuficienciaProfesionales_PE


Ficheros en el ítem

Thumbnail
Thumbnail
Thumbnail

Este ítem aparece en la(s) siguiente(s) colección(ones)

Mostrar el registro sencillo del ítem

info:eu-repo/semantics/openAccess
Excepto si se señala otra cosa, la licencia del ítem se describe como info:eu-repo/semantics/openAccess