dc.identifier.citationPortal, E. (2020). Factores que incrementan el costo de inversión de los proyectos de infraestructura vial, durante el ciclo de ejecución, modalidad de contrata, gobierno regional Cajamarca-sede central, periodo 2012-2018 (Tesis de licenciatura). Repositorio de la Universidad Privada del Norte. Recuperado de https://hdl.handle.net/11537/27544es_PE
dc.identifier.other624.0681 PORT 2020es_PE
dc.identifier.urihttps://hdl.handle.net/11537/27544
dc.description.abstractEl Invierte.pe considera en el ciclo de inversión de un proyecto a ejecución como el tercer ciclo y comprende la elaboración del expediente técnico o documento equivalente y la ejecución física, por lo que en esta investigación se tiene como objetivo determinar los factores que incrementan el costo de inversión de los proyectos de infraestructura vial, durante el ciclo de ejecución desde aprobación de expediente técnico hasta la liquidación final de proyecto, modalidad de contrata, Gobierno Regional Cajamarca-Sede Central, periodo 2012-2018. Para lo cual se ha recogido información del proceso de ejecución de las obras de la Sub Gerencia de Supervisión y Liquidaciones; además de información de los aplicativos informáticos Sistema Invierte.pe (antes SNIP), SEACE e INFOBRAS. Así mismo indicar que la ejecución de obras públicas está normada en la Ley de Contrataciones del Estado y su Reglamento. Como resultados se ha encontrado que los principales factores que incrementan el costo de inversión durante el ciclo de ejecución, la ejecución de adicionales de obra en un 62.36%; compensación por terrenos, canteras, botaderos y facilitadores sociales en un 11.88%, reajustes por actualización de precios en un 5.81%, mayores gastos generales en un 2.08%, mayores metrados 0.15%, gastos administrativos 4.34 y un porcentaje de 13.38 correspondiente a resoluciones de contrato, procesos arbitrales y partidas deterioradas consideradas en expediente de saldo de obra.es_PE
dc.description.abstractThe Invierte.pe considers the investment cycle of a project to be executed as the third cycle and includes the preparation of the technical file or equivalent document and the physical execution, so this research aims to determine the factors that increase the investment cost of road infrastructure projects, during the execution cycle from approval of the technical file to the final settlement of the project, contract modality, Cajamarca Regional Government-Headquarters, period 2012-2018. For which information has been collected on the process of execution of the works of the Sub-Management of Supervision and Liquidations; in addition to information from the computer applications Sistema Invierte.pe (formerly SNIP), SEACE and INFOBRAS. Likewise, it should be noted that the execution of public works is regulated in the State Procurement Law and its Regulations. As results, it has been found that the main factors that increase the investment cost during the execution cycle are the execution of additional works by 62.36%; compensation for land, quarries, dumps and social facilitators by 11.88%, readjustments for price updates by 5.81%, higher general expenses by 2.08%, higher metered 0.15%, administrative expenses 4.34 and a percentage of 13.38 corresponding to resolutions of contract, arbitration proceedings and impaired items considered in the work balance file.es_PE
dc.description.uriTesises_PE
dc.formatapplication/pdfes_PE
dc.formatapplication/mswordes_PE
dc.language.isospaes_PE
dc.publisherUniversidad Privada del Nortees_PE
dc.rightsinfo:eu-repo/semantics/openAccesses_PE
dc.rightsAtribución-NoComercial-CompartirIgual 3.0 Estados Unidos de América
dc.rights.urihttps://creativecommons.org/licenses/by-nc-sa/3.0/us/
dc.sourceUniversidad Privada del Nortees_PE
dc.sourceRepositorio Institucional - UPNes_PE
dc.subjectIngeniería viales_PE
dc.subjectCostos de construcciónes_PE
dc.subjectInversiones públicases_PE
dc.titleFactores que incrementan el costo de inversión de los proyectos de infraestructura vial, durante el ciclo de ejecución, modalidad de contrata, gobierno regional Cajamarca-sede central, periodo 2012-2018es_PE
dc.typeinfo:eu-repo/semantics/bachelorThesises_PE
thesis.degree.grantorUniversidad Privada del Norte. Facultad de Ingenieríaes_PE
thesis.degree.levelTítulo Profesionales_PE
thesis.degree.disciplineIngeniería Civiles_PE
thesis.degree.nameIngeniero Civiles_PE
dc.publisher.countryPEes_PE
dc.subject.ocdehttps://purl.org/pe-repo/ocde/ford#2.01.01es_PE
thesis.degree.programPregradoes_PE
dc.description.sedeCajamarcaes_PE
renati.advisor.dni41639360
renati.advisor.orcidhttps://orcid.org/0000-0001-8198-2250es_PE
renati.author.dni80442620
renati.discipline732016es_PE
renati.jurorMosqueira Moreno, Miguel
renati.jurorVásquez Ramírez, Luis
renati.jurorGuillen Sheen, Tulio
renati.levelhttps://purl.org/pe-repo/renati/level#tituloProfesionales_PE
renati.typehttps://purl.org/pe-repo/renati/type#tesises_PE


Ficheros en el ítem

Thumbnail
Thumbnail
Thumbnail
Thumbnail

Este ítem aparece en la(s) siguiente(s) colección(ones)

Mostrar el registro sencillo del ítem

info:eu-repo/semantics/openAccess
Excepto si se señala otra cosa, la licencia del ítem se describe como info:eu-repo/semantics/openAccess