dc.identifier.citationCarrera, L. R., & Mamani, D. J. (2023). Implementación Last Planner System con BIM en el marco de la productividad y control de costos, en el proyecto multifamiliar Central Home 20 pisos, ubicado en Lima 2023 [Tesis de licenciatura, Universidad Privada del Norte]. Repositorio de la Universidad Privada del Norte.https://hdl.handle.net/11537/35201es_PE
dc.identifier.other624.92 MAMA 2023es_PE
dc.identifier.urihttps://hdl.handle.net/11537/35201
dc.description.abstractLa presente investigación tiene como objetivo determinar la influencia de la implementación Last Planner System con BIM en el marco de la productividad y control de costos, en el proyecto multifamiliar Central Home 20 pisos, ubicado en Lima 2023. Por otro lado, la metodología tuvo un enfoque cuantitativo con diseño no experimental explicativo, cuyo procedimiento se realizó en una obra de edificación tipo multifamiliar de 20 niveles, a través de la metodología LPS en conjunto con BIM, para mejorar la productividad y control de costos y tiempo del proyecto. Dentro de los resultados de la investigación, se obtuvo una disminución del 2.15% en el costo directo respecto al presupuesto tradicional y se logró una optimización de 22 días respecto del cronograma tradicional; respecto a la especialidad de estructuras del proyecto. Finalmente, la variación de productividad presentó influencia positiva, partiendo desde la optimización del factor tiempo en más del 20% de días del plazo inicial. En conclusión, se determinó que la productividad y control de costos implementando LPS con BIM fue favorable, tanto el plazo de ejecución como el costo del proyecto; debido que tuvieron una variación positiva, lo que garantiza el uso de esta metodología en futuras investigaciones.es_PE
dc.description.abstractThe objective of this research is to determine the influence of the Last Planner System implementation with BIM in the framework of productivity and cost control, in the Central Home 20-story multifamily project, located in Lima 2023. On the other hand, the methodology had a quantitative approach with an explanatory non-experimental design, the procedure of which was carried out in a 20-story multi-family building project, through the LPS methodology in conjunction with BIM, to improve productivity and cost control and project time. Within the results of the research, a 2.15% decrease in the direct cost was obtained with respect to the traditional budget and an optimization of 22 days was achieved with respect to the traditional schedule; regarding the specialty of project structures. Finally, the variation in productivity presented a positive influence, starting from the optimization of the time factor in more than 20% of the days of the initial deadline. In conclusion, it was determined that productivity and cost control by implementing LPS with BIM was favorable, both the execution time and the cost of the project; because they had a positive variation, which guarantees the use of this methodology in future research.es_PE
dc.description.uriTesises_PE
dc.formatapplication/pdfes_PE
dc.formatapplication/msword
dc.language.isospaes_PE
dc.publisherUniversidad Privada del Nortees_PE
dc.rightsinfo:eu-repo/semantics/openAccesses_PE
dc.rights.urihttps://creativecommons.org/licenses/by-nc-sa/3.0/us/*
dc.sourceUniversidad Privada del Nortees_PE
dc.sourceRepositorio Institucional - UPNes_PE
dc.subjectProyectos de construcciónes_PE
dc.subjectIngeniería . Estimación de costeses_PE
dc.subjectControl de gestiónes_PE
dc.subjectProductividades_PE
dc.subjectEdificacioneses_PE
dc.subjectLast Planner Systemes_PE
dc.subjectBIM methodologyes_PE
dc.subjectProductivityes_PE
dc.subjectCost controles_PE
dc.subjectBuildingses_PE
dc.titleImplementación Last Planner System con BIM en el marco de la productividad y control de costos, en el proyecto multifamiliar Central Home 20 pisos, ubicado en Lima 2023es_PE
dc.typeinfo:eu-repo/semantics/bachelorThesises_PE
thesis.degree.grantorUniversidad Privada del Norte. Facultad de Ingenieríaes_PE
thesis.degree.levelTítulo Profesionales_PE
thesis.degree.disciplineIngeniería Civiles_PE
thesis.degree.nameIngeniero Civiles_PE
dc.publisher.countryPEes_PE
dc.subject.ocdehttps://purl.org/pe-repo/ocde/ford#2.01.01es_PE
thesis.degree.programPregradoes_PE
dc.description.sedeBreñaes_PE
renati.advisor.dni45417237
renati.advisor.orcidhttps://orcid.org/0000-0003-1609-1704es_PE
renati.author.dni44599215
renati.author.dni47147614
renati.discipline732016es_PE
renati.jurorNeyra Torres, Jose Luis
renati.jurorManturano Chipana, Ruben Kevin
renati.jurorCampos Vasquez, Neicer
renati.levelhttp://purl.org/pe-repo/renati/level#tituloProfesionales_PE
renati.typehttp://purl.org/pe-repo/renati/type#tesises_PE
dc.relation.conformsto18%es_PE


Ficheros en el ítem

Thumbnail
Thumbnail
Thumbnail
Thumbnail
Thumbnail
Thumbnail
Thumbnail

Este ítem aparece en la(s) siguiente(s) colección(ones)

Mostrar el registro sencillo del ítem

info:eu-repo/semantics/openAccess
Excepto si se señala otra cosa, la licencia del ítem se describe como info:eu-repo/semantics/openAccess