dc.contributor.advisorSangama Suazo, Saul
dc.contributor.authorNinahuanca Garay, Luis Enrique
dc.date.accessioned2024-01-17T21:37:12Z
dc.date.available2024-01-17T21:37:12Z
dc.date.issued2023-07-12
dc.identifier.citationNinahuanca, L. E. (2023). Implementación de un aplicativo móvil y su influencia en el área de calidad para la reducción de tiempo de liberación de la partida de estructuras en proyectos multifamiliares [Tesis de licenciatura, Universidad Privada del Norte]. Repositorio de la Universidad Privada del Norte. https://hdl.handle.net/11537/35614es_PE
dc.identifier.other624.068 NINA 2023es_PE
dc.identifier.urihttps://hdl.handle.net/11537/35614
dc.description.abstractLa presente tesis de investigación busca determinar la reducción de tiempo de liberación de las partidas de estructura por las complejidades de los proyectos a revisar por las diferentes partidas realizadas en campo y el costo por revisión de protocolos. El estudio tuvo como objetivo general determinar en qué medidas influye el aplicativo móvil Power apps la mejorar el costo y el plazo, la eficiencia y eficacia en la construcción del proyecto multifamiliar “INTENSE”. La metodología fue cuantitativa, aplicada, descriptiva y no experimental. La construcción fue de sótano 1 hasta tercer nivel más azotea, con una duración de 60 días, se aplicó la observación directa y el análisis documental los costó directo ante el aplicativo móvil con un valor de S/ 2.553,822.34 y su promedio diario de S/ 73,764.86.con gasto por revisión de protocolos de S/ 2,458.83 Después del aplicativo Power apps su valor fue de S/ 40,980.48 y su promedio diario fue de S/ 1,366.02. El tiempo de revisión fue representa un aumento de 375.70 minutos de tiempo productivo promedio antes del Power apps a 393.40 minutos después del Power apps; de la misma forma que de 211.00 minutos de tiempo contributivo promedio antes del Power apps a 296.43 minutos después del Power apps. En cuanto al tiempo no contributivo promedio, el mismo disminuyó de 164.70 minutos antes del Power apps a 96.97 minutos después del Power apps. Ello significa un aumento de 4.71% (tiempo productivo) y de 40.49% (tiempo contributivo), y una reducción de 58.88% (tiempo no contributivo). El aplicativo móvil mejoró significativamente la eficiencia y la eficacia. En cuanto a la eficiencia, la misma pasó de un 62% antes de la aplicación del Power apps a un 82% después de la aplicación. Y en cuanto a la eficacia, pasó de 0.78 antes del Power apps a 1.00 después del Power apps. El aplicativo móvil mejoro significativamente el costo de revisión y plazo de revisión, eficiencia y eficacia en el proyecto multifamiliar “intense”es_PE
dc.description.abstractThis research thesis seeks to determine the reduction in the release time of the structural items due to the complexities of the projects to be reviewed due to the different items carried out in the field and the cost per protocol review. The general objective of the study was to determine which measures the mobile application Power apps influences to improve the cost and time, efficiency and effectiveness in the construction of the "INTENSE" multifamily project. The methodology was quantitative, applied, descriptive and non-experimental. The construction was from basement one to third level plus roof, with a duration of 60 days, direct observation was applied and the documentary analysis cost them directly before the mobile application with a value of S/ 2,553,822.34 and its daily average of S / 73,764.86. With expenses for reviewing protocols of S/ 2,458.83 After the Power apps application, its value was S/ 40,980.48 and its daily average was S/ 1,366.02. Review time was an increase from 375.70 minutes of average productive time before Power Apps to 393.40 minutes after Power Apps; in the same way that from 211.00 minutes of average contributory time before Power apps to 296.43 minutes after Power apps. Regarding the average non-contributory time, it decreased from 164.70 minutes before Power apps to 96.97 minutes after Power apps. This means an increase of 4.71% (productive time) and 40.49% (contributory time), and a reduction of 58.88% (non-contributory time). The mobile app significantly improved efficiency and effectiveness. Regarding efficiency, it went from 62% before the application of Power apps to 82% after the application. And in terms of efficiency, it went from 0.78 before Power apps to 1.00 after Power apps. The mobile application significantly improved the review cost and review time, efficiency and effectiveness in the "intense" multifamily project.es_PE
dc.description.uriTesises_PE
dc.formatapplication/pdfes_PE
dc.formatapplication/mswordes_PE
dc.language.isospaes_PE
dc.publisherUniversidad Privada del Nortees_PE
dc.rightsinfo:eu-repo/semantics/openAccesses_PE
dc.rightsAtribución-NoComercial-CompartirIgual 3.0 Estados Unidos de América*
dc.rights.urihttps://creativecommons.org/licenses/by-nc-sa/3.0/us/*
dc.sourceUniversidad Privada del Nortees_PE
dc.sourceRepositorio Institucional - UPNes_PE
dc.subjectGestión de la construcciónes_PE
dc.subjectIndustria de la construcciónes_PE
dc.subjectControl de gestiónes_PE
dc.subjectEstándares de calidades_PE
dc.subjectAplicativo móvil internoes_PE
dc.subjectProcesos operativoses_PE
dc.subjectRetraso de liberación de estructuraes_PE
dc.subjectInternal mobile applicationes_PE
dc.subjectOperational processeses_PE
dc.subjectStructure release delayes_PE
dc.titleImplementación de un aplicativo móvil y su influencia en el área de calidad para la reducción de tiempo de liberación de la partida de estructuras en proyectos multifamiliareses_PE
dc.typeinfo:eu-repo/semantics/bachelorThesises_PE
thesis.degree.grantorUniversidad Privada del Norte. Facultad de Ingenieríaes_PE
thesis.degree.levelTítulo Profesionales_PE
thesis.degree.disciplineIngeniería Civiles_PE
thesis.degree.nameIngeniero Civiles_PE
dc.publisher.countryPEes_PE
dc.subject.ocdehttps://purl.org/pe-repo/ocde/ford#2.01.01es_PE
thesis.degree.programPregradoes_PE
dc.description.sedeBreñaes_PE
renati.advisor.dni47225221
renati.advisor.orcidhttps://orcid.org/0000-0002-0369-3936es_PE
renati.author.dni47498866
renati.discipline732016es_PE
renati.jurorNeyra Torres, Jose Luis
renati.jurorVereau Miranda, Edmundo
renati.jurorCampos Vasquez, Neicer
renati.levelhttp://purl.org/pe-repo/renati/level#tituloProfesionales_PE
renati.typehttp://purl.org/pe-repo/renati/type#tesises_PE
dc.relation.conformsto17%es_PE


Files in this item

Thumbnail
Thumbnail
Thumbnail
Thumbnail
Thumbnail
Thumbnail

This item appears in the following Collection(s)

Show simple item record

info:eu-repo/semantics/openAccess
Except where otherwise noted, this item's license is described as info:eu-repo/semantics/openAccess