dc.identifier.citation | Centurión, L. A. (2016). Eficiencia del proyecto ejecutado en la instalación de geomembrana en plataforma de lixiviación en comparación con el proyecto inicial Lagunas Norte fase 6 (Tesis de licenciatura). Repositorio de la Universidad Privada del Norte. Recuperado de http://hdl.handle.net/11537/9937 | es_PE |
dc.identifier.other | 624 CENT 2016 | es_PE |
dc.identifier.uri | https://hdl.handle.net/11537/9937 | |
dc.description.abstract | RESUMEN
Durante esta investigación, se ejecutaron diversos procesos como la observación,
evaluación y determinación de la eficiencia del proyecto a partir de la instalación de la
geomembrana, dentro de la plataforma de lixiviación fase 6, en comparación con el
proyecto inicial, ubicadas en lagunas norte a 130 km. de Trujillo, departamento de La
Libertad durante el periodo 2015-2016. Esto responde, fundamentalmente, a que es la
segunda partida más importante, después de movimiento de tierras, y, por consiguiente,
sus costos y eficiencia influyen en el proyecto. En consecuencia, repercute en la
productividad, logrando una buena planificación, desde el inicio del proyecto, se evita
pérdidas y demoras de la obra. De otro lado, para el análisis de los costos y periodo de
producción de la plataforma de lixiviación, se usó el método descriptivo y el muestreo por
conveniencia, el cual permitió conocer el procedimiento de la instalación del sistema de
revestimiento así como los presupuestos y tiempos ejecutados en comparación con lo que
se tenía previsto, mediante tablas y gráficos se determinó la eficiencia del sistema de
revestimiento en 0.671, concluyendo que fue ineficiente en el transcurso de 8 meses. Por
último, el sistema de revestimiento ejecutado fue, significativamente, mayor en costos a lo
previsto en (US $) 433, 728.68. Incrementando en 59.60%, debido a los cambios ocurridos
en el diseño durante su construcción.
PALABRAS CLAVE: eficiencia, instalación del sistema de revestimiento, costos, tiempo. | es_PE |
dc.description.abstract | ABSTRACT
During this research, various processes such as observation, evaluation and determination
of project efficiency from the installation of the liner within the leach pad phase 6, compared
with the initial project were implemented, located in lakes north 130 km. Trujillo, La Libertad
department during the period 2015-2016. This reflects mainly it is the second most
important, after earthworks, split and therefore its cost and efficiency influence the project.
Consequently, affects productivity, achieving good planning from the start of the project,
losses and delays of the work is avoided. On the other hand, for the analysis of costs and
production period of the leach pad, the descriptive method and convenience sampling,
which allowed the procedure of installation of the coating system as well as budgets and
time used implemented compared with what was planned, using tables and graphs
efficiency of the coating system was determined in 0671, concluding that it was inefficient
in the course of 8 months. Finally, the coating system was implemented, significantly higher
costs as provided in (US $) 433, 728.68. I increasing by 59.60% due to changes in design
during construction.
KEYWORDS: efficiency, coating system installation, cost, time. | es_PE |
dc.description.uri | Tesis | es_PE |
dc.format | application/pdf | es_PE |
dc.language.iso | spa | es_PE |
dc.publisher | Universidad Privada del Norte | es_PE |
dc.rights | info:eu-repo/semantics/embargoedAccess | es_PE |
dc.source | Universidad Privada del Norte | es_PE |
dc.source | Repositorio Institucional - UPN | es_PE |
dc.subject | Análisis de costos | es_PE |
dc.subject | Planificación | es_PE |
dc.subject | Estudio del trabajo | es_PE |
dc.title | Eficiencia del proyecto ejecutado en la instalación de geomembrana en plataforma de lixiviación en comparación con el proyecto inicial Lagunas Norte fase 6 | es_PE |
dc.type | info:eu-repo/semantics/bachelorThesis | es_PE |
thesis.degree.grantor | Universidad Privada del Norte. Facultad de Ingeniería | es_PE |
thesis.degree.level | Título Profesional | es_PE |
thesis.degree.discipline | Ingeniería Civil | es_PE |
thesis.degree.name | Ingeniero Civil | es_PE |
dc.publisher.country | PE | es_PE |
dc.subject.ocde | https://purl.org/pe-repo/ocde/ford#2.01.01 | es_PE |
thesis.degree.program | Pregrado | es_PE |
dc.description.sede | Cajamarca | es_PE |
renati.advisor.dni | 26733060 | |
renati.advisor.orcid | https://orcid.org/0000-0003-2668-4909 | es_PE |
renati.author.dni | 41041315 | |
renati.discipline | 732016 | es_PE |
renati.level | https://purl.org/pe-repo/renati/level#tituloProfesional | es_PE |
renati.type | https://purl.org/pe-repo/renati/type#tesis | es_PE |