dc.identifier.citationRuiz, W. M. (2020). Planta de shotcrete vía húmeda para optimizar y reducir costos en minería subterránea, La Libertad, 2020 [Tesis de licenciatura, Universidad Privada del Norte]. Repositorio de la Universidad Privada del Norte. https://hdl.handle.net/11537/28354es_PE
dc.identifier.other658.1552 RUIZ 2020es_PE
dc.identifier.urihttps://hdl.handle.net/11537/28354
dc.description.abstractEl desarrollo de esta investigación se basó principalmente en determinar cómo influye el diseño y localización de una planta de shotcrete vía húmeda en los costos en minería subterránea, La Libertad 2020, actualmente su planta de shotcrete se encuentra ubicado en superficie siendo su transporte con mixer de 3.00 m3 desde superficie a interior mina en una distancia de 5.00 km por la rampa principal Rp. 940 con una gradiente de 15%, siendo esto una demora en el ciclo del sostenimiento y que incrementa los costos. Por ello se planteó diseñar una planta de shotcrete en interior mina para evitar el tiempo de recorrido, que sumado es de 10 km entre ida y vuelta más los tiempos de pases de vehículos, y de esta manera se logró optimizar el rendimiento de todo el sistema de sostenimiento con shotcrete como también la reducción del precio del transporte y tiempo por metro cúbico. La propuesta de esta planta fue para las operaciones de la veta Lourdes y Rosa que consumen la cantidad de 80 m3/día. Las dimensiones del área donde se ubicó la planta de shotcrete, es de 30.00 m de largo por 8.00 m de ancho con una altura de 10.00 m más dos chimeneas de 16.00 m cada una, siendo una de arena y otra de cemento la que será alimentada por 6 viajes de arena de shotcrete por volquetes de 15.00 m3 y cemento a granel en big bag de 1 tonelada transportado por plataforma grúa. La calidad de la roca donde se realizó dicho proyecto para la planta de shotcrete dio un RMR de 36 a 38, con un diseño de sostenimiento combinado de shotcrete de 2”, pernos swellex de 8” más pernos helicoidales de 10” separados de 1.00 m x 1.00 m. La minera subterránea tenía el sistema de sostenimiento mecanizado con shotcrete vía húmeda el cuál se prestó satisfactoriamente al método de explotación usado en esta mina.es_PE
dc.description.abstractThe development of this research was based mainly on determining how the design and location of a wet shotcrete plant influences costs in underground mining, La Libertad 2020, currently its shotcrete plant is located on the surface and its transport is with a mixer of 3.00 m3 from surface to inside mine in a distance of 5.00 km along the main ramp Rp. 940 with a gradient of 15%, this being a delay in the sustainability cycle and which increases costs. For this reason, it was proposed to design a shotcrete plant in the interior of the mine to avoid travel time, which in addition is 10 km between round trips plus vehicle pass times, and in this way it was possible to optimize the performance of the entire system of support with shotcrete as well as the reduction of the transport price and time per cubic meter. The proposal for this plant was for the Lourdes and Rosa vein operations that consume the amount of 80 m3 / day. The dimensions of the area where the shotcrete plant was located is 30.00 m long by 8.00 m wide with a height of 10.00 m plus two 16.00 m chimneys each one, being one of sand and the other of cement, which will be fed by 6 trips of shotcrete sand by 15.00 m3 dump trucks and bulk cement in a 1-ton big bag transported by platform crane. The quality of the rock where this project was carried out for the shotcrete plant gave an RMR of 36 to 38, with a combined support design of 2 "shotcrete, 8" swellex bolts plus 10 "helical bolts separated by 1.00 mx 1.00 m. The underground mine had a mechanized wet shotcrete support system which was satisfactorily lent to the exploitation method used in this mine.es_PE
dc.description.uriTesises_PE
dc.formatapplication/pdfes_PE
dc.formatapplication/mswordes_PE
dc.language.isospaes_PE
dc.publisherUniversidad Privada del Nortees_PE
dc.rightsinfo:eu-repo/semantics/openAccesses_PE
dc.rightsAtribución-NoComercial-CompartirIgual 3.0 Estados Unidos de Américaes_PE
dc.rights.urihttps://creativecommons.org/licenses/by-nc-sa/3.0/us/*
dc.sourceUniversidad Privada del Nortees_PE
dc.sourceRepositorio Institucional - UPNes_PE
dc.subjectCostoses_PE
dc.subjectTransportees_PE
dc.subjectIngeniería geológicaes_PE
dc.subjectMineríaes_PE
dc.titlePlanta de shotcrete vía húmeda para optimizar y reducir costos en minería subterránea, La Libertad, 2020es_PE
dc.typeinfo:eu-repo/semantics/bachelorThesises_PE
thesis.degree.grantorUniversidad Privada del Norte. Facultad de Ingenieríaes_PE
thesis.degree.levelTítulo Profesionales_PE
thesis.degree.disciplineIngeniería de Minases_PE
thesis.degree.nameIngeniero de Minases_PE
dc.publisher.countryPEes_PE
dc.subject.ocdehttps://purl.org/pe-repo/ocde/ford#2.07.05es_PE
thesis.degree.programPregradoes_PE
dc.description.sedeTrujillo San Isidroes_PE
renati.advisor.dni41779520
renati.advisor.orcidhttps://orcid.org/0000-0002-8348-8624es_PE
renati.author.dni47080490
renati.discipline724026es_PE
renati.jurorAlcalá Adrianzén, Miguel Enrique
renati.jurorZelada Mosquera, Danny Stephan
renati.jurorLuján Túpez, Julio Augusto
renati.levelhttps://purl.org/pe-repo/renati/level#tituloProfesionales_PE
renati.typehttps://purl.org/pe-repo/renati/type#tesises_PE


Ficheros en el ítem

Thumbnail
Thumbnail
Thumbnail
Thumbnail

Este ítem aparece en la(s) siguiente(s) colección(ones)

Mostrar el registro sencillo del ítem

info:eu-repo/semantics/openAccess
Excepto si se señala otra cosa, la licencia del ítem se describe como info:eu-repo/semantics/openAccess